July 30, 2018
Efficiency is always an important part of getting the job done, however with certain systems such as Accelera®, the curing time can be much faster than a small crew can handle.
In these instances it is best to not multi-task and instead bring a properly sized crew for each position.
For best results on a maximum 40 foot wet edge include:
- 1 person mixing
- 1 person running pails
- 1 person on squeegee
- 1 person cross-rolling
- 1 person broadcasting for every 15 linear feet of wet edge
Additional manpower will be required for complex installations requiring cut-in work.
Gardner Perry
Applicator Development